[Brahms-l] Fw: Acting Scheduling Physicist News: Maintenance Tuesday

From: flemming videbaek <videbaek@rcf.rhic.bnl.gov>
Date: Tue Apr 19 2005 - 09:04:06 EDT
As you can see thare will be a full access day today Tuesday.
We did, I believe most of the work neede during an 2h access last Friday, but there may be some loose
end to figure out
- mrst0 counter ..
- issues of tpm2 readout.

flemming

----------------------------------------------------------------
Flemming Videbaek
Physics Department
Brookhaven National Laboratory

e-mail: videbaek@bnl.gov
phone: 631-344-4106
----- Original Message ----- 
From: Kin Yip 
To: kinyip@fnal.gov 
Sent: Monday, April 18, 2005 11:01 AM
Subject: Acting Scheduling Physicist News: Maintenance Tuesday


Hi,

We'll have a full day Maintenance Day tomorrow (Tuesday, Apr. 19, 2005). 
Everybody (polarimeter group, vacuum group, Maintenance coordinator etc.) seems to be 
ready to install the new silicon detector for the CNI polarimeter in RHIC.   The reasoning to do this
right away is to replace the present damaged silicon detector so that we can have more reliable
polarization measurements, at least to the minds of some experimenters.

It is said that the cold snake in AGS should be cold enough and ready for installation etc 
tomorrow, too.

Acting Scheduling Physicist,

Kin Yip




_______________________________________________
Brahms-l mailing list
Brahms-l@lists.bnl.gov
http://lists.bnl.gov/mailman/listinfo/brahms-l
Received on Tue Apr 19 08:56:42 2005

This archive was generated by hypermail 2.1.8 : Tue Apr 19 2005 - 08:57:04 EDT