From: Flemming Videbaek (videbaek@sgs1.hirg.bnl.gov)
Date: Wed May 21 2003 - 15:06:04 EDT
Dear Collaborator,
Presumably this will be the final schedule change. 
At the same time an updated shift schedule by posted and we just manage to cover the shifts
for the remaining period. The physics running should resume late this evening.
regards
    Flemming
"
enc/
from Phil Pile
The 40 hour pp2pp run has been extended by 9 hours and is set to end at 2100
hrs tonight. The "final" RHIC schedule is as follows:
 
21 May, 2100 hrs - end pp2pp, restore normal RHIC pp operations
 
27 May - 4 hour maintenance (if necessary)
 
30 May, 0800 hrs - end stores for RHIC experiments, begin beam experiments
 
30 May, 1600 hrs - begin RHIC shutdown (NEW)
 
~ 3 June - begin AGS experiment E963 (proton radiography)
 
~ 13 June - end E963
 
15 June - NYPA/LIPA 2003 Curtailment Program in effect, 31 MW power limit
for BNL (AGS & LINAC must be off)
best regards,
Phil
"
------------------------------------------------------
Flemming Videbaek
Physics Department
Brookhaven National Laboratory
tlf: 631-344-4106
fax 631-344-1334
e-mail: videbaek@bnl.gov
This archive was generated by hypermail 2.1.5 : Wed May 21 2003 - 15:05:20 EDT