Shifter leader was SB
Shifters were 


1. Beam from previous night shift continued throughout the day. RHIC went to machine development around 2:20 pm
2. FS@2.3 deg @1/1A
   trig2(182k), trig3(574k), trig4(128k), trig5(225k)
3. No major detector problems. Bottom channels 13 and 14 of H2 were incorrectly cabled. Flemming put them back in their orginal configuration.