Part of the early cooldown is going well so the most likely scenario is given below- moved up about 4 days compared to the last schedule. So for all of you coming and stying over the socalled Holidays there should real datatking to look forward to. regards Flemming This slide is from Phil Pile and to be shown at todays meeting. .Overall Plan (based on presidential budget) Ø18 Nov 04 - Cryo on Ø19 May 04 - RHIC Run 4 ends Ø26 May 04 - RHIC cryo switched to LN2 (27 weeks total) .Details - as run/planned (some details based on '04 run and are subject to change) Ø18 Nov 04 - Cool down begins Ø25 23 Nov 04 - Blue Ring Cold Ø2 Dec 28 Nov 04 - Yellow Cold Ø3 Dec 29 Nov - "2 week" RHIC setup with beam begins Ø16 12 Dec 04 - "2 week" ramp-up with colliding beams begins .Late evening stores for experiments .2, 8 hr accesses for experiments if needed (based on last year's plan) Ø30 26 Dec 04 - 8 week physics with 100 GeV/n x 100 GeV/n Cu-Cu begins .12 Jan 05 - First experiment access, bi-weekly thereafter (all up to 8 hrs and only if needed) .5 Jan 05 - First beam experiment, weekly thereafter (up to 12 hrs/week) Ø24 Feb 05 - Nominal end of 8 week Cu-Cu run Ø24 Feb 05 - begin 3 week pp setup Ø17 Mar 05 - Begin 9 week pp Physics run Ø19 May 05 - end 9 week pp run, RHIC Run 5 ends Ø26 May 04 - Cryo switch to LN2 complete, 27 weeks of RHIC cryo operation ends ---------------------------------------------------------------- Flemming Videbaek Physics Department Brookhaven National Laboratory e-mail: videbaek@bnl.gov phone: 631-344-4106 _______________________________________________ Brahms-l mailing list Brahms-l@lists.bnl.gov http://lists.bnl.gov/mailman/listinfo/brahms-lReceived on Wed Nov 24 08:54:21 2004
This archive was generated by hypermail 2.1.8 : Wed Nov 24 2004 - 08:54:45 EST