[Brahms-l] Fw: SPY news update: Apr. 6-8 for the 3 day Jet Target installation ... 63 / 31.4 ... probably still alive after May 7

From: flemming videbaek <videbaek@rcf.rhic.bnl.gov>
Date: Sat Mar 13 2004 - 09:41:12 EST
FYI

----------------------------------------------------------------
Flemming Videbaek
Physics Department
Brookhaven National Laboratory

e-mail: videbaek@bnl.gov
phone: 631-344-4106
----- Original Message ----- 
From: Kin Yip 
To: kinyip@fnal.gov 
Sent: Friday, March 12, 2004 8:57 PM
Subject: SPY news update: Apr. 6-8 for the 3 day Jet Target installation ... 63 / 31.4 ... probably still alive after May 7




====== Scheduling Physicist -YIP (ie. SPY) news channel ========

(1) Apr. 6-8 for the 3 day Jet Target installation 

The gold-gold run ends and the polarized-proton run starts on Apr. 2, 
2004 at 08:00 (in the morning).   

This does NOT mean that the 3 day Jet Target installation day
starts on Apr. 2, 2004 !     I didn't say when we would start the 3 day
installation period in my last email as the situation was not very clear.
Now, it's a bit clearer.

Mei Bai et. al. will run the RHIC with polarized-protons for the first 
4 days (from Apr. 2) WITHOUT the Jet Target.   The Jet Target is
planned to be installed during the 3 day period, from Apr. 6 (Tuesday)
to Apr. 8 (Thursday); and actually many other works such as those 
of the RF cavities will be done during these 3 days.    

During these 3 days, there may be ( I said "may be" !) an 8 hour period
for an AGS access which is driven by the works related to the CNI
polarimeter in the AGS.  The polarimeter group has not finally decided
and they'll re-evaluate about one week before Apr. 6.

Booster needs to be run and can't be shut down during the above 3 day period
as the NSRL (NASA) program needs Booster !  

There is a LIPA test which needs to be done during one of the above 3 days.
People are trying to figure out how to run the Booster and (if necessary) AGS
at the same time of this ~12 hour LIPA test.  I understand that we may switch
Booster to the "preferred feed" from the nominal "alternate feed".


   *******************  ********************  **********************

(2) 63 GeV ?

63 GeV (in 2 significant digits) is the Center-Of-Mass energy for the 
coming lower energy gold-gold run starting from Apr. 2, 2004  and     
the Beam Energy is half of that.

Slightly more precise if you like, the exact value we use for the 
center-of-mass energy is 62.8 GeV and the beam energy is 
62.8/2 = 31.4 GeV.

   *******************  ********************  **********************

(3) NSRL (NASA) schedule maneuver

Since we need to fix a switch in the 3L sub-station on Mar. 17, 2004
and the Booster will be off, NSRL program will have to stop for ~a day.

Yesterday (Thursday) morning, when I thought about the lower energy
run schedule, I realized that since we need to dedicate 2-3 days (starting
from Mar. 24) for the machine development for the lower energy run, 
we can't practically run the NSRL experiments during those 3 days.   
Because NSRL by that time will want to have the Fe ion beams and 
delivering Fe ion beams to NSRL cannot co-exist with the injection to RHIC.
During the machine development period, there is no considerable period of 
RHIC stores (during which there is no RHIC injection) but just 
injection followed by injection most of the time.

I immediately inform the run-coordinators for the RHIC & NSRL and other
people about this news --- I hope they could tell me that I was wrong but
unfortunately I was right this time.   So  now, the plan is that NSRL 
experiments will be shifted to be done during the weekend.

   *******************  ********************  **********************

(4) Other brief status (as I see it) ... probably still alive after May 7:

  --- We've had a tough afternoon that the main ramping power supply for the RHIC
       yellow ring keeps pulling the quench link (which prevents us from running).
       Experts are trying to cure this problem at the time of writing.

  --- Independently, it seems that we have got a working mode with pulses of 
      gold ions (from the MP7 Tandem) and a pulse of silicon ions (from the MP6 
      Tandem).  This way, both the RHIC and NSRL operation can co-exist 
      (even during RHIC injection).  This mode is only possible for silicon and 
      carbon ions during the RHIC gold operation.

  --- Also, the polarized-proton run setup operation in the AGS continues.   

  --- Conflicts with different programs become more apparent.  But as usual, we
       are doing our best to cope with each other.    

Well, I predict that I'll still be alive after May 7, 2004 when the RHIC gold-gold 
run, polarized-proton run and the NSRL run all finish according to our present 
schedule.  Life just goes on ...............


   *******************  ********************  **********************

(5) As usual, the next Time meeting is next Tuesday (Mar. 16, 2004) 
    at 13:30 in the Snyder Seminar Room.


====== ======= ====== ======= ====== ======= ====== =======

This SPY news channel solicits YOUR input of any sorts.
You'll be paid back with loads of gratefulness :-)

Let me know if you want to get out of this private email mailing list.

SPY's webpage :

http://www.c-ad.bnl.gov/kinyip/SchedPhys/

=================================================================

Disclaimer: Whatever is being said here is not always 100% accurate 
though I try my best to avoid being 100% inaccurate :-)






_______________________________________________
Brahms-l mailing list
Brahms-l@lists.bnl.gov
http://lists.bnl.gov/mailman/listinfo/brahms-l



Ivy.gif
Received on Sat Mar 13 09:36:02 2004

This archive was generated by hypermail 2.1.8 : Sat Mar 13 2004 - 09:36:23 EST