From: Brendan Fox (fox@drax.Colorado.EDU)
Date: Mon Jun 30 2003 - 18:38:40 EDT
Hi y'all, Here is my summary of today's (Monday, June 30th) RHIC Spin Collaboration Meeting. - brendan ========================================================================= (1) Did we reach saturation of luminosity and polarization during the pp running in Run-03 where saturation is being defined relative to what could be achieved with current understanding and hardware? - Luminosity No, the bunch currents were 0.7e11; we could probably have reached 1.0e11 which, for 50 bunches, reaches the 1e13 limit on total current (sum of both rings) which arises from the vaccuum pressure rise and subsequent severe background issues at the experiments. Two more weeks of running without any concerns of polarization would have been helpful on this matter. - Polarization Yes. (2) What are critical machine issues for Au-Au? - bunch merging in the booster to bring up the Au intensity to 1e9 * this involves stacking bunches in the booster and requires improvements to the rF system. These improvements are underway during the current shutdown. * by stacking bunches, we draw more ions from the tandem and there is a worry about the foils in the source. This is likely not an issue for Run-4 since you have two tandems, so, if one goes out, you can use the other while working on the down one. * since the bunches will be stacked longitudinally, it is important to control the longitudinal emittance; otherwise, one cannot stack as many "initial" bunches into a single "final" bunch. This matter needs to be studied. - storage rF * this was improved during the dA run by eliminating some noise in the the system. * during the dA running, the three common mode cavities was not used since the two species do not have the same requirements. So, these cavities will provide additional power per beam in Run-04. However, the tuning of the common mode cavities is trickier because both beams are affected by the same cavities. * during Run-3, especially near the end of the pp run, the storage rF tripped off often. These trips were likely a result of having lost one of the windows in the rF system. All of the other windows survived so it is likely that this window was just the weakling. So, this should not be as much of problem in Run-04. * in the past, the storage rF cavities have also served as Landau cavities during the ramp. This year, dedicated Landau cavities are being installed. * as a goal, they aim to squeeze the longitudinal profiles so that 60 and 65% of the collision vertices are usable at PHENIX. - stochastic cooling * this idea addresses issues of growth of the bunch during a store. * there is a plan to install a kicker & pickup at 12:00 and 4:00 during this shutdown so that the use of schochastic cooling can be studied during Run-04. - the NEG coating and addressing the pressure rise problem * focusing on the areas most affected by the pressure rise problem, the plan is to coat 60m of approximately 700m of warm section in RHIC with a NEG coating during this summer. This coating will serve as a getter which will sucks up residual gas and holds it better. * some possible side effects: coating could affect the impedance of the machine, might affect the pumping (though that should be a positive not negative effect), and one needs to think about how the hydrogen jet target and the coating co-exist - beam lifetime Unlike in p-p, Au-Au is not as affected by the beam-beam interaction because its Z/A is 0.4 that of p. The issue for Au+Au is more one of intrabeam interaction. From simultuations, the lifetime is expected to be ~1.5 hours for Au-Au with 1e9 ions per bunch. (3) What are critical machine issues for p-p? - polarization from the AGS * for Run-4, the warm helical snake will be in place. With this, they expect to raise the AGS polarization from ~0.4 to ~0.5 for the same bunch emittance of ~10pi seen in Run-3. To achieve this emittance without massively scrapping the bunches in the booster as was needed during Run-3, thinner stripping foils are being installed in the booster. - polarization in RHIC * going from injection to store, we typically lost ~25% of the polarization (i.e. 40%->30%). It is believed that this loss occurred during the beta* squeeze as opposed to along the energy ramp. This opinion is based on a few ramps in which there was no beta* squeeze and no loss of polarization. The data need to be checked to see if the conclusion is completely true or whether there was also loss on the ramp. * tune control and, maybe, orbit control The tune control was not reliably operational until near the end of the run. When it was, it controlled the tune quite well during the ramp. Having such control will certainly improve the polarization retention. It is expected to be used regularly in Run-4. * tune to a new working point Putting the working point between the 3/14 (0.21) and 1/4 (0.25) spin resonances results in a more limited tune space than is available at ~0.195. So, tuning to a lower working point may benefit polarization retention. However, such a point where the machine is stable has to be identified first. Presently, they are working on simulations to locate this point. Questions which arose were: o can you simulate the beam-beam tune shift effects accurately? Absolutely, maybe not. But, relatively, is the goal. Learning that one working point is better relative to another is sufficient at this time to make progress on this matter. o would having different working points per species be an issues? Probably not. o would you also tune Au-Au to the new working point if this point is found? If there was a big gain, probably yes. However, Au-Au is not limited by beam-beam interactions, so it is unlikely that there is a big gain out there for it. o would a change in the working point affect the tune feedback control (PLL) system? Probably yes though, in principle, the system should handle it gracefully, but we would need to see how things. (4) In a p+p commissioning run in Run-04, what would be the key items which would be pursued? - in AGS: * tuning for polarization with the weak snake - in RHIC: * understanding the beam-beam interaction by: (A) testing new working point to have more tune space to work in (B) improving the non-linear corrections to reduce the size of the resonances * test of the Ng coating to control the pressure rise when pushing bunch intensities past 1e11 * 250 GeV ramp * spin flipper commissioning As Waldo pointed out, we have been commissioning the spin flipper on "when convenient" basis. Since the experiments do see crossing-by-crossing differences, we might consider allocating a reasonable amount of commissioning time to bring it up to an operational state. * grow the emittance during the or end of the ramp so that lower emittance bunches can be ramped in the AGS (good for polarization) and then become higher emittance bunches when colliding in RHIC (good for luminosity) * the polarized hydrogen jet target needs a shakedown run (5) What is the amount of time needed to do this commissioning? Thomas said that they would need 5 weeks (which includes the setup time) to do the necessary studies. People questioned whether this time was sufficient and whether collisions at experiments were needed to assure that what is learned from these studies would be representative of the future performance. Thomas agreed to think about how much "experiment" running would be needed on this front. (6) What is a reasonable scenario to use as a "success" model for developing the beam-use proposal? We had a long discussion about this matter and we'll be returning to it again when we get together in roughly 2 weeks.
This archive was generated by hypermail 2.1.5 : Mon Jun 30 2003 - 18:39:21 EDT