From: Brendan Fox (fox@drax.Colorado.EDU)
Date: Mon Jun 30 2003 - 18:38:40 EDT
Hi y'all,
Here is my summary of today's (Monday, June 30th) RHIC Spin Collaboration
Meeting. 
								- brendan
=========================================================================
 (1) Did we reach saturation of luminosity and polarization during the pp
     running in Run-03 where saturation is being defined relative to what
     could be achieved with current understanding and hardware?
     - Luminosity
       No, the bunch currents were 0.7e11; we could probably have
       reached 1.0e11 which, for 50 bunches, reaches the 1e13 limit
       on total current (sum of both rings) which arises from the vaccuum
       pressure rise and subsequent severe background issues at the
       experiments.  Two more weeks of running without any concerns of
       polarization would have been helpful on this matter.
     - Polarization
       Yes.
 (2) What are critical machine issues for Au-Au?
     - bunch merging in the booster to bring up the Au intensity to 1e9 
       * this involves stacking bunches in the booster and requires
         improvements to the rF system.  These improvements are underway
         during the current shutdown.
       * by stacking bunches, we draw more ions from the tandem and there
         is a worry about the foils in the source.  This is likely not an
         issue for Run-4 since you have two tandems, so, if one goes out, 
         you can use the other while working on the down one.
       * since the bunches will be stacked longitudinally, it is important to
         control the longitudinal emittance; otherwise, one cannot stack
         as many "initial" bunches into a single "final" bunch.  This matter
         needs to be studied.
     - storage rF
       * this was improved during the dA run by eliminating some noise in the
         the system.  
       * during the dA running, the three common mode cavities was not used
         since the two species do not have the same requirements.  So,
         these cavities will provide additional power per beam in Run-04.
         However, the tuning of the common mode cavities is trickier because
         both beams are affected by the same cavities.
       * during Run-3, especially near the end of the pp run, the storage rF
         tripped off often.  These trips were likely a result of having lost
         one of the windows in the rF system.  All of the other windows
         survived so it is likely that this window was just the weakling.
         So, this should not be as much of problem in Run-04.
 
       * in the past, the storage rF cavities have also served as Landau
         cavities during the ramp.  This year, dedicated Landau cavities are
         being installed.
       * as a goal, they aim to squeeze the longitudinal profiles so that 
         60 and 65% of the collision vertices are usable at PHENIX.
     - stochastic cooling
       * this idea addresses issues of growth of the bunch during a store.
       * there is a plan to install a kicker & pickup at 12:00 and 4:00 during
         this shutdown so that the use of schochastic cooling can be studied
         during Run-04.  
     - the NEG coating and addressing the pressure rise problem
       * focusing on the areas most affected by the pressure rise problem, the
         plan is to coat 60m of approximately 700m of warm section in RHIC
         with a NEG coating during this summer.  This coating will serve as a 
         getter which will sucks up residual gas and holds it better.  
       * some possible side effects: coating could affect the impedance of the
         machine, might affect the pumping (though that should be a positive
         not negative effect), and one needs to think about how the hydrogen
         jet target and the coating co-exist
     - beam lifetime
       Unlike in p-p, Au-Au is not as affected by the beam-beam interaction
       because its Z/A is 0.4 that of p.  The issue for Au+Au is more one of
       intrabeam interaction.  From simultuations, the lifetime is expected
       to be ~1.5 hours for Au-Au with 1e9 ions per bunch.
 (3) What are critical machine issues for p-p?
     - polarization from the AGS
       * for Run-4, the warm helical snake will be in place.  With this, they
         expect to raise the AGS polarization from ~0.4 to ~0.5 for the same
         bunch emittance of ~10pi seen in Run-3.  To achieve this emittance
         without massively scrapping the bunches in the booster as was needed 
         during Run-3, thinner stripping foils are being installed in the
         booster. 
     - polarization in RHIC
       * going from injection to store, we typically lost ~25% of the
         polarization (i.e. 40%->30%).   
         It is believed that this loss occurred during the beta* squeeze as
         opposed to along the energy ramp.  This opinion is based on a few
         ramps in which there was no beta* squeeze and no loss of
         polarization.  The data need to be checked to see if the conclusion
         is completely true or whether there was also loss on the ramp.
       * tune control and, maybe, orbit control
         The tune control was not reliably operational until near the end of
         the run.  When it was, it controlled the tune quite well during the
         ramp.  Having such control will certainly improve the polarization
         retention.  It is expected to be used regularly in Run-4.
       * tune to a new working point
         Putting the working point between the 3/14 (0.21) and 1/4 (0.25) spin
         resonances results in a more limited tune space than is available 
         at ~0.195.  So, tuning to a lower working point may benefit
         polarization retention.  However, such a point where the machine
         is stable has to be identified first.  Presently, they are working on
         simulations to locate this point.  Questions which arose were:
         o can you simulate the beam-beam tune shift effects accurately?
           Absolutely, maybe not.  But, relatively, is the goal.  Learning
           that one working point is better relative to another is sufficient
           at this time to make progress on this matter. 
         o would having different working points per species be an issues?
           Probably not.
         o would you also tune Au-Au to the new working point if this point
           is found?
           If there was a big gain, probably yes.  However, Au-Au is not
           limited by beam-beam interactions, so it is unlikely that there is 
           a big gain out there for it. 
         o would a change in the working point affect the tune feedback
           control (PLL) system?
           Probably yes though, in principle, the system should handle it
           gracefully, but we would need to see how things.
 (4) In a p+p commissioning run in Run-04, what would be the key items which
     would be pursued?
     - in AGS:
       * tuning for polarization with the weak snake
     - in RHIC: 
       * understanding the beam-beam interaction by:
         (A) testing new working point to have more tune space to work in
         (B) improving the non-linear corrections  to reduce the size of the
             resonances
       * test of the Ng coating to control the pressure rise when pushing 
         bunch intensities past 1e11
       * 250 GeV ramp
       * spin flipper commissioning
         As Waldo pointed out, we have been commissioning the spin flipper
         on "when convenient" basis.  Since the experiments do see 
         crossing-by-crossing differences, we might consider allocating a 
         reasonable amount of commissioning time to bring it up to an
         operational state.
       * grow the emittance during the or end of the ramp so that lower
         emittance bunches can be ramped in the AGS (good for polarization)
         and then become higher emittance bunches when colliding in
         RHIC (good for luminosity)
       * the polarized hydrogen jet target needs a shakedown run
 (5) What is the amount of time needed to do this commissioning?
     Thomas said that they would need 5 weeks (which includes the setup time)
     to do the necessary studies.  People questioned whether this time was
     sufficient and whether collisions at experiments were needed to assure
     that what is learned from these studies would be representative of the
     future performance.  Thomas agreed to think about how much "experiment"
     running would be needed on this front.
 (6) What is a reasonable scenario to use as a "success" model for developing
     the beam-use proposal?
     We had a long discussion about this matter and we'll be returning to it
     again when we get together in roughly 2 weeks.
This archive was generated by hypermail 2.1.5 : Mon Jun 30 2003 - 18:39:21 EDT