RHIC plans and schedule for remaining run.

From: Flemming Videbaek (videbaek@sgs1.hirg.bnl.gov)
Date: Tue May 06 2003 - 09:44:29 EDT

  • Next message: Jens Jørgen Gaardhøje: "Re: RHIC plans and schedule for remaining run."
    There has been disucsions in the RHIC spin group, i.e., in essence the two big exp + CA-D + pp2pp , even though we have a small say
    about the utilization of the remaining ~10 days of the run. The plan as stands now given below. It is quite aggressive plan
    that aims primarely as I see it to commision and having a long-shot of an A-LL measurement (delta-G) for STAR. 
    It should be recalled that the primary reason for not cutting the pp run short was to get polarization measurements.
    
    The summary plan is (but of course it can also be changed)
    
    The 'planned schedule is
    
    5/6,5/7,5/8 (until 19:00) Physcis runnning with present config.
    5/8 19:00- 5/9 8:00 Beam experiment
    5/9 (Friday) 8 hour access (star spin-rotator work + ice-ball chasing)
    5/9-5/11 morning/midday spin rotator commisioning - No collisions (5-6 shifts)
    5/11-5/14 morning - physics running 
    5/14-5/16 pp2pp setup+running
    
    
    regards
        Flemming
    
    
    ------------------------------------------------------
    Flemming Videbaek
    Physics Department
    Brookhaven National Laboratory
    
    tlf: 631-344-4106
    fax 631-344-1334
    e-mail: videbaek@bnl.gov
    


    This archive was generated by hypermail 2.1.5 : Tue May 06 2003 - 09:40:50 EDT