about the utilization of the remaining ~10 days of the run. The plan as stands now given below. It is quite aggressive plan
that aims primarely as I see it to commision and having a long-shot of an A-LL measurement (delta-G) for STAR. 
It should be recalled that the primary reason for not cutting the pp run short was to get polarization measurements.
The summary plan is (but of course it can also be changed)
The 'planned schedule is
5/6,5/7,5/8 (until 19:00) Physcis runnning with present config.
5/8 19:00- 5/9 8:00 Beam experiment
5/9 (Friday) 8 hour access (star spin-rotator work + ice-ball chasing)
5/9-5/11 morning/midday spin rotator commisioning - No collisions (5-6 shifts)
5/11-5/14 morning - physics running 
5/14-5/16 pp2pp setup+running
regards
    Flemming
------------------------------------------------------
Flemming Videbaek
Physics Department
Brookhaven National Laboratory
tlf: 631-344-4106
fax 631-344-1334
e-mail: videbaek@bnl.gov
This archive was generated by hypermail 2.1.5 : Tue May 06 2003 - 09:40:50 EDT