Shift report 20020110 00:00-08:00

From: Apache (apache@pii3.brahms.bnl.gov)
Date: Thu Jan 10 2002 - 08:17:46 EST

  • Next message: Flemming Videbaek: "Fw: New PHENIX paper on HBT"

    ------------------------------------------------------------
    Date: Thu Jan 10 08:17:46 2002, Shift: 00:00-08:00
    Supervisor: KH, with: 
    Log book#12 pages 36 - 39
    
    Shift Summary:
    ------------------------------------------------------------
    Machine Status:
    Beam during most of the night.  A store had started
    at 22:50 and continued until 5:10 at which point PHENIX
    and us voted to dump.  Beam was stored and cogged again
    at 7:00.  
    
    Achievements:
    Run    trig 3  trig 6
    6394    210k    98k   MRS 40 4B; FS 12 1/8B; ended at 5:10
    
    Changed FS field to 1/4B before beam came back
    
    Started run 6397 at 7:00 when beam came back with L-1, R-1 Inelastic triggers removed from the main trigger.  Rates were reasonable.  But DAQ crashed at 7:30 with a run error
    which I didn't understand.  I managed to get it back
    by restarting IoServer and RunServer.
    
    After investigation, I decided
    it was probably the result a degraded beam quality.  The
    singles Inel rate L and R is about 300k!  Currents in 
    T3 were very high.  They are slowly coming down as is the 
    rate.  At time of writing, they have come back down to 
    reasonable levels, so I will stop run 6397 and start a new
    one for the next shift.
    ------------------------------------------------------------
    