    FYI.
    
    at tomorrows access we are planning to complete the installation of the MRS back trigger slats and a needed
    checkout of the fron trigger slat.
    
    
    ------------------------------------------------------
    Flemming Videbaek
    Physics Department
    Brookhaven National Laboratory
    
    tlf: 631-344-4106
    fax 631-344-1334
    e-mail: videbaek@bnl.gov
    ----- Original Message ----- 
    From: Angelika Drees 
    Sent: Wednesday, December 19, 2001 4:39 PM
    Subject: update
    
    
    Hi, 
    in RHIC we have our last day of dedicated commissioning where we did tests with experimental magnets, worked on orbits and RF. Later tonight we'll continue working on ramps. If you need an access around midnight, please contact MCR in time - for the time being I don't have anybody on my list so we might not open up. 
    
    Tomorrow morning we have restricted access in the IRs from 8:00-13:00. Sweeps are done from 13:00 on and should be done by 15:00 when we resume operation with beam. PHENIX should be swept last. We'll reconvene with PHENIX after the access and come up with a plan for further access needs for  the next few days. Please check  the scheduling physicist webpage (http://www.cadops.bnl.gov/AP/RHIC2001/SchedPhys/) for possible scenarios. 
    
    In the AGS we keep working on polarization improvements and horizontal emittance.  Currently we can maintain 30% (the goal is 50%) at extraction energy which could be confirmed in RHIC at injection in both rings. We'll continue with this efforts behind RHIC stores during the production stores. For the time being the polarization in RHIC at flattop might be still much below 30 %. We'll measure polarization for every store at injection and storage. These measurements will be online available to experiments. 
    
    Next week we won't have a time meeting (I know, you were looking forward to a special christmas day time meeting ;) ). I'll keep you posted via webpage and emails instead. Seasonal greetings, 
    
    -- 
                                                    \|/
                     Angelika                      (.~.)
                                                  o0(_)0o
    -----------------------------------------------------------
    Angelika Drees (Collider-Accelerator Department, AP group)
    BNL, Building 911b-210
    work: (631) 344 2348
    FAX:  (631) 344 5954      
    home: (631) 474 3884
      
    



    This archive was generated by hypermail 2b30 : Fri Dec 21 2001 - 08:56:56 EST