Date: Fri Sep 21 08:00:06 2001, Shift: 00:00-08:00
Supervisor: EJ, with: DS
Log book#9 pages 19 - 20
Shift Summary:
------------------------------------------------------------
1. Beam for 5 hours (to 2:30 and 4:25-7:00). Beam shut
down due to lightning.
2. #4835 ( 80K trig 1 events.)
#4836 ( 88K trig 1 events.)
#4837 (246K trig 1 events.)
#4838 ( 44K trig 1 events.)
----
458K
3. Same problems at with last run - no connection to main
frame (TILES4 and TILES5). Connection to L1458B was
somehow lost. We turned it back on.
------------------------------------------------------------