------------------------------------------------------------ Date: Mon Aug 7 07:58:07 2000, Shift: 00:00-08:00 Supervisor: DO, with: ZIS Log book#4 pages 21 - 22 Shift Summary: ------------------------------------------------------------ 1.MC dumped the beam at 1:00. They worked on injection, did a ramp that failed. Problems of quench interlock in the blue ring. Power dip from 2:30 up to now. 2.The only achievement is run 2080 started at 20:42 (previous shift) and stopped at 00:50. 3.No new problems (mainframe FFS1440 still unreachable) BB delta time still shows a shift Collision rate low ------------------------------------------------------------