Summary
All systems in prototype or production phase.
Total estimated project cost is within budget and completion by RHIC turnon is within schedule.
Completion of spectrometer arm 2 will depend on use of contingency and new funding.
Most major procurements complete.
Magnet must be installed and mapped on time or detector installation will be seriously delayed.
PHOBOS looking forward to physics running on day 1.