Schedule
Nov 3: Magnet arrives @ BNL
Nov 3 - Dec 2: Commissioning of magnet @ AGS:
- Assembly of components
- Interlock sensors
- Manifolding & Buss-bars
- B-field and mechanical tests @ full power
Dec 7: Move magnet to RHIC
Dec 8 - 18: Commissioning of magnet @ RHIC
- Power and cooling
- Hook up with RHIC controls
Dec 21 - Jan 29, ‘99: Mapping of magnet