Shifter leader was kh
Shifters were 


Had beam from shift start at 8:00 until about 11:00.
Achieved runs 16148 through 16151 which were mrs 45 deg 1050B and fs 3 deg 1/2B.
At the end of the store, they did a vernier scan which we managed to capture.  It was in run 16152.
There were various machine problems afterwards and there is still no beam at shift end.