Dear Collaborators, The 62 GeV run is approaching. The current schedule for the run is Mon. June 5th 2 pm End 200 GeV run Begin 22 GeV test run (Ggamma=21.5) Tue. June 6th 2 pm End 22 GeV test run Begin 62.4 GeV setup Thur. June 8th 4 pm Begin 62.4 GeV Physics run Tue. June 20th 6 pm End 62.4 GeV run Begin 500 GeV test run Mon. June 26th 6 am End 500 GeV run Begin Warm Up to LN temperature. The latest schedule can be found at the Run06 Scheduling Physicists page: http://www.agsrhichome.bnl.gov/SchedPhys/FY2006/ The shift schedule can be found at http://brahms-web.brahms.bnl.gov/shift/shifts/CurrentShiftList.htm If you have a problem with the schedule, please let me know. We took a few stores at 200 GeV last week for setting-up detectors and timing. The data set taken yesterday, which covers the missing 4deg. 1/4B at 200 GeV, can be considered as physics data set. A Vernier scan was done at BRAHMS at the end of the store yesterday also. (See the e-log for details.) Cheers, JH _______________________________________________ Brahms-l mailing list Brahms-l@lists.bnl.gov http://lists.bnl.gov/mailman/listinfo/brahms-lReceived on Mon Jun 5 10:50:37 2006
This archive was generated by hypermail 2.1.8 : Mon Jun 05 2006 - 10:50:50 EDT