[Brahms-l] RHIC Schedule

From: J.H. Lee <jhlee@rcf.rhic.bnl.gov>
Date: Wed Dec 28 2005 - 11:13:11 EST
Dear Collaborators,

The "current" RHIC schedule discussed at the Time Meeting yesterday
can be found at the RUN6 scheduling physicist's (Kevin Brown) web page:
http://www.agsrhichome.bnl.gov/SchedPhys/FY2006/  .

*Dec. 27^th , 2005:*
Current Schedule:
Tuesday, December 27^th , Restart RHIC Scrubbing. Begin starting up 
systems in preparation for polarized protons.
Monday, January 9^th , RHIC Cooldown to 80K begins.
Tuesday, January 3^th , Linac begins turn on for polarized protons.
Monday, January 16^th , AGS Turn on for polarized proton setup.
Monday, January 23^th , RHIC Dry Run.
Monday, January 30^th , RHIC Cooldown to 4K begins.
Monday, February 6^th , Blue ring ready for beam.
Monday, February 13^th , Yellow ring ready for beam.
Wednesday, March 1^st , Begin NSRL-06A.
 
Cheers, JH



_______________________________________________
Brahms-l mailing list
Brahms-l@lists.bnl.gov
http://lists.bnl.gov/mailman/listinfo/brahms-l
Received on Wed Dec 28 11:14:06 2005

This archive was generated by hypermail 2.1.8 : Wed Dec 28 2005 - 11:14:20 EST