Shifter leader was rk Shifters were Peaceful night with plenty of data taken. 1. Had beam from the beginning of shift, dump scheduled at 0633 but had been delayed due to problems with LINAC injector - hence still running. 2. Runs: 14825 - 14835 - full field B, FS@2.3, MRS@90. 3. None observed. _______________________________________________ Brahms-l mailing list Brahms-l@lists.bnl.gov http://lists.bnl.gov/mailman/listinfo/brahms-lReceived on Sun May 22 08:03:43 2005
This archive was generated by hypermail 2.1.8 : Sun May 22 2005 - 08:03:54 EDT