 - There was no beam during this shift. Machine development and then
   equipment failures. Current status "Machine setup".
                                                                                
 - Only pedestal runs: 14405, 14406
                                                                                
 - TPC's and Drift chambers are in park mode.
   All magnets set in StandBy.