[Brahms-l] Shift report 20050312 08:00-16:00

From: <apache@brahms-web.brahms.bnl.gov>
Date: Sat Mar 12 2005 - 16:49:46 EST
Shifter leader was JHL
Shifters were 


Beam: for 6h2m
-1:00
2:40-  
staring wit ZDC ~1.5K

Data:
FS 4deg. 1219B Setting Done: 500K Trigger2
Currently FS 3deg. 1723B: Goal 300K Trigger2
MRS 90deg. 700A

Problem: 
Lost ~1hour beam time due to SBE6 and TPC readout error.
DAQ is back and running.

_______________________________________________
Brahms-l mailing list
Brahms-l@lists.bnl.gov
http://lists.bnl.gov/mailman/listinfo/brahms-l
Received on Sat Mar 12 16:50:13 2005