[Brahms-l] Shift report 20050216 00:00-08:00

From: <apache@brahms-web.brahms.bnl.gov>
Date: Wed Feb 16 2005 - 07:49:53 EST
Shifter leader was SZ
Shifters were 


1. No beam from the entry of shift. It came arround 1:30 (physiscs Running)

2. RUNS:

- MRS@40, FFS@4, BFS@4:


13202 - tr2=201k, tr3=100k
13203 - tr2=221k, tr3=175k
13204 - tr2= 47k, tr3= 55k
13205 - tr2=264k, tr3=131k
13206 - tr2=142k, tr3=132k
---------------------------
SUM     tr2=875k, tr3=596k

 
Monitor Summary Plots:

http://brahms-web.brahms.bnl.gov/shift/MonitorSummary/run05/R013202/
http://brahms-web.brahms.bnl.gov/shift/MonitorSummary/run05/R013203/
http://brahms-web.brahms.bnl.gov/shift/MonitorSummary/run05/R013204/
http://brahms-web.brahms.bnl.gov/shift/MonitorSummary/run05/R013205/
http://brahms-web.brahms.bnl.gov/shift/MonitorSummary/run05/R013206/

Summary BrNtuple Plots:

http://brahms-web.brahms.bnl.gov/shift/summary/R013202/
http://brahms-web.brahms.bnl.gov/shift/summary/R013203/
http://brahms-web.brahms.bnl.gov/shift/summary/R013204/
http://brahms-web.brahms.bnl.gov/shift/summary/R013205/
http://brahms-web.brahms.bnl.gov/shift/summary/R013206/

E-log Shift Page: 

http://brahms-web.brahms.bnl.gov/cgi-bin/elog.pl?nb=2005&action=view&page=116&scroll=false


3. No detector problems

_______________________________________________
Brahms-l mailing list
Brahms-l@lists.bnl.gov
http://lists.bnl.gov/mailman/listinfo/brahms-l
Received on Wed Feb 16 07:50:36 2005