[Brahms-l] Scheduling Physicist News: X/Y arc set-up starts Friday night

From: flemming videbaek <videbaek@rcf.rhic.bnl.gov>
Date: Tue Nov 16 2004 - 09:34:19 EST
----------------------------------------------------------------
Flemming Videbaek
Physics Department
Brookhaven National Laboratory
FYI:

I should also inform you that JH will be the primary BRAHMS representative
at the two weekly coordination meeting
i) Monday's at 3 pm which is the weekly planning meeting, settling access
times,..
and
ii) wednesday corrdination meeting with BNL /CAD management reporting
overall progress and setting
goals and general guide lines for the running.


The overall RHIC schedule is not completely clear. The accident certainly
mean a delay for startup , but how much is unclear.
The scheduled Blue rung cold is now 11/25, and yellow 11/30+-1 day. This is
about 10 - 7 days late, but may or may not end up in
a similar delay for the physics startup.

regards
    Flemming


e-mail: videbaek@bnl.gov
phone: 631-344-4106
----- Original Message ----- 
From: "Christoph Montag" <montag@bnl.gov>

Sent: Monday, November 15, 2004 3:54 PM
Subject: Scheduling Physicist News: X/Y arc set-up starts Friday night


> Set-up of the X/Y arcs is scheduled as overnight work, starting Friday
> November 19. "Overnight" means 8 PM to 8 AM; during this time RHIC plus
> its experimental areas needs to be swept. We expect to need up to four
> nights for this set-up.
>
> -- 
>
> Christoph Montag, Brookhaven National Laboratory
> Building 911B, P.O. Box 5000, Upton, NY 11973, U.S.A.
> Phone: +1-631-344-4820
> http://www.agsrhichome.bnl.gov/SchedPhys/Montag/schedphys.html
>
>


_______________________________________________
Brahms-l mailing list
Brahms-l@lists.bnl.gov
http://lists.bnl.gov/mailman/listinfo/brahms-l
Received on Tue Nov 16 09:33:50 2004

This archive was generated by hypermail 2.1.8 : Tue Nov 16 2004 - 09:34:14 EST