FYI I have attached the notes + a table from Phil Pile outlining the present
run plan allowing for
25 RHIC cryo weeks. Note also the summary of the coordination meeting as of
yesterday


Flemming

*** From Phil Pile, CA-D

> Follow-up to the below notes...
>
> RHIC cryo work begins with a full nitrogen cool down of the RHIC magnets
on
> 14 Oct. Any schedule changes should be decided before that date (our
target
> date is then the wednesday meeting before this --- 13 Oct) - by request, I
> have attached the week-by-week schedule I presented at the meeting..
> best regards,
> Phil
>
>
> -----Original Message-----
> From: Pile, Philip H
> Sent: Wednesday, September 29, 2004 3:48 PM
> To: Lo Presti, Penny; Aronson, Samuel; Bai, Mei; Baker, Mark; Beavis,
Dana;
> Bond, Peter D; Brennan, Joseph; Bunce, Gerry M; 'busza@mit.edu'; Butler,
> Michael A; Christie, William; Drees, K. Angelika; Fischer, Wolfram;
Gibbard,
> Bruce; Gordon, Howard A; 'Gulshan.Rai@science.doe.gov';
> 'gunther.roland@cern.ch'; Guryn, Wlodzimierz; Hallman, Timothy J;
Heimerle,
> Marion V; 'hofman@uic.edu'; Huang, Haixin;
> 'Jehanne.Simon-Gillo@science.doe.gov'; 'jhthomas@lbl.gov'; Kirk, Thomas B;
> 'lajoie@iastate.edu'; Lee, Jeong-Hun; Ljubicic, Ante; Lowenstein, Derek I;
> Ludlam, Thomas W; Mackay, William W; Makdisi, Yousef I;
'matthias@bnl.gov';
> Montag, Christoph; O'Brien, Edward; Ozaki, Satoshi; Pak, Robert; Peggs,
> Stephen G; 'peter.steinberg@bnl.gov'; Petway, Annabelle; Pilat, Fulvia C;
> Roser, Thomas; 'saito@nh.scphys.kyoto-u.ac.jp'; Samios, Nicholas P;
> Satogata, Todd J; Throwe, Thomas; Trbojevic, Dejan; Videbaek, Flemming;
> 'vigdor@iucf.indiana.edu'; Yamin, Peter; Yip, Kin; 'younggr@ornl.gov';
Zajc,
> William; Zukowski, Elaine D
> Subject: RHIC Machine & Experiments Meeting Wednesday, September 22, 2004
>
>
> A short note on some of the discussion in today's meeting:
>
> (1) All systems are still on track for a 8 Nov cool-down start.
>
> (2) On the issue of the appropriate time lag between the end of a given
RHIC
> run and the RHIC Program Committee meeting charged with giving advice on
> beams for the next run...The consensus was the program committee meeting
> should not be held sooner than about 2 months after the close-out meeting
> for the previous run. The close-out meeting generally occurs about a month
> after the end of a run, so for example, if RUN5 ends on 30 April then the
> program committee meeting to decide the type and order of ions for the
next
> run should optimally be scheduled in August. This gives the experiments
> enough time to formally decide on their respective beam requests.
>
> (3) There was a brief discussion of when data analysis of RUN4 would come
to
> an end. The experiments agreed that the bulk of the analysis should be
> completed by the time of the next Quark Matter conference (next Summer)
with
> some targeted analysis completed much sooner.
>
> (4) There was discussion about a further delay to the start of RUN5. The
> logic is a further delay may allow enough time for Congress to enact the
> FY2005 budget so that planning for RUN5 can properly take into account
> available funds. It was recognized that a decision on this should be made
> about 2 weeks prior to the 8 Nov cool-down date in order to minimize
> disruption of work activities. This will continue to be a topic of
> discussion at the next few Wednesday Meetings.
>
> best regards,
> Phil
>
>

_______________________________________________
Brahms-l mailing list
Brahms-l@lists.bnl.gov
http://lists.bnl.gov/mailman/listinfo/brahms-l



Received on Fri Oct 1 11:20:16 2004

This archive was generated by hypermail 2.1.8 : Fri Oct 01 2004 - 11:20:40 EDT