[Brahms-l] Fw: SPY news update: Time meeting Tuesday (Mar. 2) ...Schedule ... challenge the smoothness of our operation ...

From: flemming videbaek <videbaek@rcf.rhic.bnl.gov>
Date: Mon Mar 01 2004 - 19:40:02 EST
FYI
mainly along the lines what I already send out.
Flemming

----------------------------------------------------------------
Flemming Videbaek
Physics Department
Brookhaven National Laboratory

e-mail: videbaek@bnl.gov
phone: 631-344-4106
----- Original Message ----- 
From: Kin Yip 
To: kinyip@fnal.gov 
Sent: Monday, March 01, 2004 6:10 PM
Subject: SPY news update: Time meeting Tuesday (Mar. 2) ...Schedule ... challenge the smoothness of our operation ...




====== Scheduling Physicist -YIP (ie. SPY) news channel ========

(1) The usual Time meeting will happen again on Mar. 2, 2004 (Tuesday)
      in the Snyder Room (911A).

    ***********************************************************

(2) This week's schedule looks like :

  Tuesday :    Beam Expts.                      20:00 - 07:00 (Wed.)
 Wednesday: Scheduled Maintenance   07:00 - 15:00
  Thursday:    Machine Development    09:00 - 16:00 --- subject to 
                       cancellation and shortening

    ***********************************************************

(3) Brief status (in my view):

We've had overall a great week of luminosity (at the highest level 
~> 150 inverse microbarn a week depending whether you count  
between two Monday's or two Sunday's or two Tuesday's).   But
we have had some problems in the weekend with the collimator,
Tandom source and water leak in the STAR expt. area etc.

The AGS/Booster is really busy.  In principle, this week, it's mainly
for the polarized-proton set-up; next week, it's mainly for the NSRL 
(NASA) set-up.  But we need to do "bunch-merging" exercise.  Today, 
we've also tested the Booster beam operation with D6 septum on and off.

Apparently, our colleagues are working in a very civilized way to try to
accomplish all the impossible goals at the same time.

    ***********************************************************

(4) AGS access .... Challenging the smoothness of our operation ...

At the time of writing, we have the 2nd AGS access behind a RHIC store 
this run.  This has to do with fixing problems with the CNI polarimeter in the 
AGS.  Last Thursday, we had the first AGS behind a RHIC store.   
This is something that is frowned upon by various people, mainly because 
it takes ~45 minutes to put the LOTO (Log-Out/Tag-Out) to AGS at the 
beginning and another 45 minutes to take the LOTO off at the end.   If the 
RHIC store were to be aborted accidentally, we'd be wasting time (even if 
we can get those people out of the AGS ring immediately) as we'll have to 
wait for the LOTO to be taken off first before we can start the injection
business in AGS into RHIC.

This AGS feature (having to spend ~1.5 hours to open/close) is not ideal, 
to say the least for our operation --- in my opinion.

A good way of putting this AGS access behind RHIC store is probably 
to say that we are challenging the "smoothness" of our RHIC operation !

Last Thursday's AGS access, those people were to install some electronics. 
But guess what ?  Those guys' electronics were actually readyonly by ~10 am 
--- i.e. ~2 hours before they actually had that AGS access !   They didn't tell 
me that when they made that request the previous week or even a couple 
days ago --- a not very good practice.

====== ======= ====== ======= ====== ======= ====== =======

This SPY news channel solicits YOUR input of any sorts.
You'll be paid back with loads of gratefulness :-)

Let me know if you want to get out of this private email mailing list.

SPY's webpage :

http://www.c-ad.bnl.gov/kinyip/SchedPhys/








_______________________________________________
Brahms-l mailing list
Brahms-l@lists.bnl.gov
http://lists.bnl.gov/mailman/listinfo/brahms-l



Nature_Bkgrd.jpg
Received on Mon Mar 1 19:35:24 2004

This archive was generated by hypermail 2.1.8 : Mon Mar 01 2004 - 19:35:46 EST