[Brahms-l] Shift report 20040210 08:00-16:00

From: Apache <apache@bnl.gov>
Date: Tue Feb 10 2004 - 15:56:15 EST
------------------------------------------------------------
Date: Tue Feb 10 15:56:15 2004, Shift: 08:00-16:00
Supervisor: EBJ, with: 
Log book#15 pages 52 - 52

Shift Summary:
------------------------------------------------------------
1.  There was a good 4 hour store.  We took data for 2.5 hours of the store.  
2. We finished up the runs for 2.3 degrees, and moved the FS to 4 degrees. We only collected 50k at 4 degrees
3. There were no problems with the detector. 
------------------------------------------------------------

_______________________________________________