[Brahms-l] Shift report 20040110 08:00-16:00

From: Apache <apache@bnl.gov>
Date: Sat Jan 10 2004 - 15:57:31 EST
------------------------------------------------------------
Date: Sat Jan 10 15:57:31 2004, Shift: 08:00-16:00
Supervisor: Oana Ristea, with: Ionut Arsene
Log book#15 pages 29 - 29

Shift Summary:
------------------------------------------------------------
1. No beam for the entire shift. AGS power supply problems.

2. 7528 - Non TPC pedestal run
   7529 - TPC pedestal run

3. No problems detected.
------------------------------------------------------------