RE: Cooldown delay

From: Murray, Michael J (mjmurray@ku.edu)
Date: Thu Sep 25 2003 - 13:25:02 EDT

  • Next message: yin.zhongbao@fi.uib.no: "RE: Updated QM abstracts from Bergen."
       Dear Flemming,
                I could conveniantly come to BNL for the of the 15th-22nd-23rd.
    Would that be useful?
                          Michael
    PS If you see Kris and Bjorn could you remind them about our meeting
    tomorrow and ask
    if they can put stuff on the web.
    
    
    
    -----Original Message-----
    From:	Flemming Videbaek [mailto:videbaek@rcf.rhic.bnl.gov]
    Sent:	Thu 9/25/2003 10:45 AM
    To:	brahms-l@bnl.gov
    Cc:	
    Subject:	Fw: Cooldown delay
    
    Dear Collaborator,
    
    As explained below there is a delay in RHIC startup due to a cryogenic leak,
    that needs repair.
    The first estimate is a two week delay in startup, but a better and probably
    more official should come next week.
    
    Thus it seems the schedule might be the following (my interpretation)
    somewhat similar to last year,
    though one could hope that Au-Au beams will be simpler than d-Au.
    
    Dec 1 - Dec 15  2 weeks startup
    Dec 15 - Jan 3  3 week rampup (machine during day and exp setup interveaved)
    Jan 3                    Physics start
    
    
    regards
        Flemming
    
    ------------------------------------------------------
    Flemming Videbaek
    Physics Department
    Brookhaven National Laboratory
    
    tlf: 631-344-4106
    fax 631-344-1334
    e-mail: videbaek@bnl.gov
    
    ----- Original Message ----- 
    From: "Makdisi, Yousef I" <makdisi@bnl.gov>
    To: "Hallman, Timothy J" <hallman@bnl.gov>; "Christie, William"
    <christie@bnl.gov>; "'Bill Zajc'" <zajc@columbia.edu>;
    "O'Brien, Edward" <eobrien@bnl.gov>; "Baker, Mark" <mdbaker@bnl.gov>;
    "'Robert Pak'" <Robert.Pak@bnl.gov>; "Videbaek,
    Flemming" <videbaek@bnl.gov>; "Beavis, Dana" <beavis@bnl.gov>
    Cc: "Yip, Kin" <kinyip@bnl.gov>
    Sent: Thursday, September 25, 2003 10:51 AM
    Subject: FW: Cooldown delay
    
    
    | To our experimenters,
    |      The note below explains a leak in the 4 o'clock valve box and the
    | anticipated delay in the cooldown and beam startup. For the experiments,
    the
    | shield walls should be in place on November 24 at the latest.
    |
    | Regards,
    |      Yousef
    | -----Original Message-----
    | From: Roser, Thomas
    | Sent: Thursday, September 25, 2003 9:58 AM
    | To: Lowenstein, Derek I
    | Cc: Tuozzolo, Joseph E; McNerney, Andrew J; Pile, Philip H; Makdisi,
    Yousef
    | I
    | Subject: Cooldown delay
    |
    |
    | Derek,
    |
    | The repair of the leak in the Q1 current feed-through at the blue 4
    o'clock
    | valve box has started and will take about 3 weeks. Our best estimate is
    that
    | this will delay the RHIC cooldown by about 2 weeks since we can rearrange
    | the cooldown sequence. This is a best estimate and will be refined early
    | next week. The projected time for RHIC cold and ready for beam is then
    Dec.
    | 1 (was Nov. 17).
    |
    | Thomas
    |
    
    
    
    