Summary of the Friday, June 20th RSC Meeting

From: Brendan Fox (fox@drax.Colorado.EDU)
Date: Fri Jun 27 2003 - 05:19:23 EDT

  • Next message: Dana Beavis: "Re: high pt paper"
    Hi y'all,
    
    Gerry wrote up the following summary of the last week's RHIC Spin Meeting.
    
    								- brendan
    
    =========================================================================
    
                  Summary from RHIC Spin meeting of June 20, 2003
                  -----------------------------------------------
    
    The meeting was organized by Brendan Fox, and the focus was on getting
    information to develop a spin run plan for Run 4, to bring to collaborations. 
    
    Polarized gas jet target: great progress described by Yousef Makdisi
    
      -- expected to be ready for Run 4 (to be installed in summer/fall,
         then removed during gold-gold run, to work in lab; installation
         then takes 3 days for a pp run)
    
      -- 1 development silicon detector of 4 works from 1st batch (reported by
         Sandro Bravar), looking at other existing silicon of similar size from
         Hamamatsu (expected 50% to work, also issue of schedule for production
         from BNL Instrumentation)
    
    STAR spin (Les Bland): machine development and physics for Run 4
    
      -- this is only from the spin group.  STAR has not started discussions on 
         the beam use proposal yet
    
      -- machine development--toward spin goal of 30 pb^-1/week, P=0.7
    
      -- goal for Run 4 P^4 x LT > 10 nb^-1/week (10x run 3)
         -- 3/4 barrel EmCal, 3 pb^-1, P=.4
         -- physics for A_LL, jets-==>gluon polarization
    
      -- polarized gas jet ==> commission, Delta P/P to +/-10%
    
      -- STAR multi-year plan in the 02 beam use proposal was:
         -- Au-Au 19 weeks (16 weeks at root(s_NN)=200, 1 at 3 lower energies)
         --   pp   8 weeks, root(s)=200
    
      -- important to develop credible plan on luminosity and P, leading to
         direct photon program
    
      -- root(s)=500 running requires large LT to be useful, reference data
         for heavy ions important
    
    PHENIX spin (Yuji Goto): main discussion next week after info. from here
    
      -- Run 3 gave 350 nb^-1, P=.27, P^4 x LT = 1.8 nb^-1
         -- expectation on A_LL 2-3 sigma from max. gluon model
    	-- vs. 3 pb^-1, P=.4 (about 20 sigma from max. gluon pol.) (Run 2 plan)
    	-- Run 2 plan would give 20K direct photons, p_T>5, 10K J/psi,
    	   1M single e, 4K mu-mu and 7K e-mu charm events.
    
         -- root(s)=500 (discussed for run 6, vs. 200 GeV)
    	-- compared xdelta(Delta g) for 200, 500 GeV--200 GeV better
    
    BRAHMS spin (Brendan Fox): 
    
      -- Run 4 would place spectrometer at 2.3 deg., get interesting measurement  
         in 20-40 hours.
    
    RHIC summary (Haixin Huang):
    
      -- source problem early in run (ok for Run 4?)
      -- pp started March 26
      -- yellow snake failure, partial snake solution saved run
      -- physics started May 3
      -- STAR rotator commissioning May 15
      -- switch to 2 IRs May 23
      -- run ended May 30 (9 weeks total)
    
    AGS (Leif Ahrens):
    
      -- expected to reach P=.5, reached above .4
      -- intensity dependence of P not resolved (but see Mei Bei plot)
      -- lower P at end of run--not understood yet
      -- plan to use thinner stripping foil (half) into Booster to reduce
         emittance for Run 4
      -- warm snake for Run 4 (but no plan to correct weak intrinsics--issue of
         manpower, and small emittance improves pol. losses for these resonances
      -- cold snake for Run 5
    
    Q: why 2 steps?--if cold snake necessary, what do we learn from warm snake?
    A: warm snake for spin matching (but then commissioning useful in Run 4?), also
       problem seems to be strong intrinsic resonances-->replace rf dipole with
       cold snake (Thomas).
    
    RHIC polarization (Mei Bei):
    
      -- Mei shows much lower avg. P than we use--probably not throwing out
         low P runs (aborted store for low P)
      -- no correlation between P and intensity at 24 GeV in RHIC
      -- snake resonance curves--after correction, yellow (with partial snake)
         still had larger strength than blue (discussion about optimization for
         yellow done at 24 GeV after recovery from snake failure; may have been
         off of optimum at 100 GeV)
      -- 20% loss in Delta P/P at end of beta squeeze--coupling problem, plan to
         squeeze during energy ramp for Run 4, stay on histeresis curve
    
    500 GeV issues--what is possible? (Thomas Roser):
    
      -- spin resonances 2-3x stronger between 100-250 GeV, orbit corrections
         imply that we preserve P, but tight tolerances on corrections
    
      -- other issues all same as for 200 GeV--i.e. need to be solved first
    
    Plan (Thomas Roser):
    
      -- considering changing working point (fractional tune, related to both beam
         resonance space and spin resonance space)--to improve beam-beam tune 
         spread and shift issues.  Presently about .22 to .23, change to .18?
         This was the original plan, but early running had problems at this tune.
    
      -- tune feedback required to be operational--worked in Run 3, but not
         operational (delta tune to <.005 with feedback, 10x larger without
         (check))
    
      -- introduced letter from Wolfram Fisher and Thomas Roser on expected
         performance for Run 4
    
    ================================================================================
    


    This archive was generated by hypermail 2.1.5 : Fri Jun 27 2003 - 05:23:12 EDT