Dear Collaborator,
The scehdule is still in kind of flux. What has emerged is that STAR wants to complete the transverse asymmetry measurements
which requires 100 nb-1 collected (at ~30% pol in yellow). This may take anywhere between 2 and 5 days (I guess the end of run is the upper limit); Once this is done they would like to have the spin rotators commisioned.
We therefore decided to continue with being prepared to man the experiment - assuming a combination of machine improvement and
physics running continuing with the 12 deg 1/4 A and 1/2 A running. A shift list that covers the weekend + monday has been put
into place. The details for next week will depend on progress and further RHIC scheduling.
regards and hopes for a good weekend.
Flemming
------------------------------------------------------
Flemming Videbaek
Physics Department
Brookhaven National Laboratory
tlf: 631-344-4106
fax 631-344-1334
e-mail: videbaek@bnl.gov
This archive was generated by hypermail 2.1.5 : Fri May 09 2003 - 16:51:23 EDT