update from sche. phys

From: Flemming Videbaek (videbaek@rcf.rhic.bnl.gov)
Date: Mon Apr 28 2003 - 19:59:06 EDT

  • Next message: Apache: "Shift report 20030428 16:00-24:00"
    Dear Coll,
    I am forwaring the most recent message regarding the pp-run startup.
    The plan is to deliver some kind of beam soon, and progress has been made
    through the day.
    
    Flemming
    
    
    -- 
    Flemming Videbaek
    Brookhaven National Laboratory
    Physics Department
    tlf 631-344-4106
    fax 631-344-1334
    e-mail: videbaek@bnl.gov
    
    
    Hi,
    
    last night recommissioning of the rotator ramp was not successful by
    midnight and over night we were trying to tune collisions without rotators
    to no avail :(. This morning we continued our commissioning effort which
    is still going on. We will not try to collide without the rotators on but
    continue to work on the ramp until we have reasonable beam transmission
    and polarization. At this point, polarization is preserved for the first
    part of the ramp (ramp&squeeze) but lost in yellow during the rotator
    part. Blue beam does not survive rotator ramp so far.
    
    Beam experiments were postponed until next week and maintenance by one
    day to Thu, 8:00 am to 11:00 am, allowing 1 hour for sweeps. Most
    experimental areas will be on Restricted Access. During the access we'll
    do ice-ball search and swap the polarity for the STAR rotators.
    
    I'm looking forward to seeing everybody at the time-meeting tomorrow :).
    