From: Apache (apache@pii3.brahms.bnl.gov)
Date: Sat Feb 08 2003 - 08:02:13 EST
------------------------------------------------------------ Date: Sat Feb 8 08:02:13 2003, Shift: 00:00-08:00 Supervisor: kh, with: Log book#14 pages 5 - 5 Shift Summary: ------------------------------------------------------------ Beam from 3:00 through 3:45 and 7:00 through shift end Runs trig 3 trig 6 7836 57K 46K 7837 51K 20K move MRS to 40deg and change D5 to 1050A 7838 in progress Plan for next period of time: MRS: 500K at current setting (40 deg D5=1050A) 500K at 40 deg D5=1050B FS 130K at current setting (8 deg 1/4B) move FS to 12 deg 200K at 12 deg 1/8B 200K at 12 deg 1/20B 150K at 12 deg 1/4B ------------------------------------------------------------
This archive was generated by hypermail 2.1.5 : Sat Feb 08 2003 - 08:02:58 EST