Shift report 20030203 00:00-08:00

From: Apache (apache@pii3.brahms.bnl.gov)
Date: Mon Feb 03 2003 - 07:43:23 EST

  • Next message: Ian Bearden: "data reduction log"
    ------------------------------------------------------------
    Date: Mon Feb  3 07:43:23 2003, Shift: 00:00-08:00
    Supervisor: IA, with: SZ
    Log book#13 pages 143 - 144
    
    Shift Summary:
    ------------------------------------------------------------
    1. We had beam for 5 hours during the shift. 
    2. Achievements :
       Data runs :
      run 7752 - MRS 40 degrees 500(A) 413k trigger 3 events
               - FS 8 degrees 1/4A 47k
      run 7753 - MRS 40 degrees Zero field  40k
               - FS  4k 
      run 7754 - MRS 40 degrees 500(B) 150k
               - FS 18k
      run 7755 - MRS 500(B) 66k
    Need more 184k trigger 3 events at MRS 40 degrees, 500(B)
    and 103k trigger 6 events at FS 8 degrees, 1/4A
    
       Pedestal runs:
      run 7756 - Non-TPC pedestal run
      run 7757 - TPC pedestal run
      run 7758 - DVM run
    3. During the data store T1 was off because was triped in previous shift. 
    ------------------------------------------------------------
    