The lasst weekend in 2001 (fwd)

From: Flemming Videbaek (videbaek@sgs1.hirg.bnl.goV)
Date: Fri Dec 28 2001 - 23:06:56 EST

  • Next message: Apache: "Shift report 20011228 16:00-24:00"

    FYI on RHIC machine progress
    ------------------------------------------------------------------
    
    Flemming Videbaek 
    Physics department, Brookhaven national laboratory
    Upton L.I., NY11973, USA
    
    Phone: (516)-344-4106 
    FAX:   (516)-344-1334
    secr:  (516)-344-7681
    e-mail: videbaek@bnl.gov
    
    
    
    ---------- Forwarded message ----------
    Date: Fri, 28 Dec 2001 14:53:10 -0500
    From: Angelika Drees <drees@bnl.gov>
    To: Wlodek Guryn <guryn@bnl.gov>, Steve Peggs <peggs@bnl.gov>,
         Naohito Saito <saito@spin.riken.bnl.gov>, Robert Pak <Robert.Pak@bnl.gov>,
         Dejan Trbojevic <dejan@bnl.gov>, Fulvia Pilat <pilat@bnl.gov>,
         Mike Harrison <harrison@bnl.gov>, Steve Tepikian <tepikian@bnl.gov>,
         Waldo MacKay <mackay@bnl.gov>, Angelika Drees <drees@bnl.gov>,
         Vadim Ptitsyn <vadimp@bnl.gov>, Ted D'Ottavio <dottavio@bnl.gov>,
         Roger Katz <rak@bnl.gov>, John Morris <jtm@bnl.gov>,
         Peter Ingrassia <ingrassia@bnl.gov>, Paul Sampson <sampson@bnl.gov>,
         Mei Bai <mbai@bnl.gov>, Bruce Gibbard <gibbard@bnl.gov>,
         Leif Ahrens <ahrens@bnl.gov>, Woody Glenn <jglenn@bnl.gov>,
         John Gould <gould@bnl.gov>, Thomas Roser <roser@bnl.gov>,
         Andy McNerney <mcnerney@bnl.gov>, Marion Heimerle <heimerle@bnl.gov>,
         Kevin A. Brown <kbrown@bnl.gov>, Yousef Makdisi <makdisi@bnl.gov>,
         Derek Lowenstein <lowenstein@bnl.gov>, S.Y. Lee <shylee@indiana.edu>,
         Peter Paul <ppaul@bnl.gov>, Ila Campbell <ila@bnl.gov>,
         Aki Yokosawa <AY@hep.anl.gov>, Alan Carroll <acarroll@bnl.gov>,
         Albert Hanson <alh@bnl.gov>, Betsy Sutherland <bms@bnl.gov>,
         Chris Morris <cmorris@lanl.gov>, Dana Beavis <BEAVIS@hi2>,
         Penny Lo Presti <lopresti@bnl.gov>, Michael Butler <butler1@bnl.gov>,
         Wuzheng Meng <meng@bnl.gov>, Wesley Buxton <buxton1@bnl.gov>,
         Tom Ludlam <Ludlam1@bnl.gov>, Tom Kirk <tkirk@bnl.gov>,
         Satoshi Ozaki <Ozaki@bnl.gov>, Tom Russo <russo2@bnl.gov>,
         Ralf Prigl <prigl@bnl.gov>, Phil Pile <pile@bnl.gov>,
         Peter Yamin <yamin@bnl.gov>, Peter Thieberger <pt@bnl.gov>,
         Neville Williams <neville@bnl.gov>, Mike Iarocci <mikei@bnl.gov>,
         Mike Brennan <brennan1@bnl.gov>, Kevin Brown <BROWN10@bnl.gov>,
         Joseph Tuozzolo <tuozzolo@bnl.gov>, Jon Sandberg <jsandberg@bnl.gov>,
         John McClelland <john@lanl.gov>, James Alessi <alessi@bnl.gov>,
         I Hung Chiang <chiang@bnl.gov>, Gerry Bunce <bunce@bnl.gov>,
         Ed Lessard <lessard@exchange.bnl.gov>,
         Donald Lazarus <lazarus@sun2.bnl.gov>, Don Barton <barton@bnl.gov>,
         Al Pendzick <Pendzick@bnl.gov>, zeps <zeps@pa.uky.edu>,
         Bill Morse <morse@bnl.gov>, watanabe <watanabe@linac.tokai.jaeri.go.jp>,
         Vernon Hughes <Hughes@hepvms2.physics.yale.edu>,
         Tomokazu Fukuda <tomokazu.fukuda@kek.jp>,
         Brad Tippens <brad.tippens@hq.doe.gov>, Tim Hallman <hallman@bnl.gov>,
         tamura <tamura@tkyvax.phys.s.u-tokyo.ac.jp>,
         Steve Kettell <kettell@bnl.gov>, Sam Aronson <aronsons@bnl.gov>,
         Adam Rusek <rusek@bnl.gov>, Robert Chrien <chrien@bnl.gov>,
         phobos coordinator <phobos_coord@mit.edu>,
         nefkens <nefkens@physics.ucla.edu>,
         michael.zeller <michael.zeller@yale.edu>,
         MCDONALD <MCDONALD@puphed.princeton.edu>,
         Marcelo Vazquez <vazquez@bnl.gov>, Lee Roberts <roberts@bu.edu>,
         Lawrence Littenberg <littenberg@bnl.gov>,
         kisimoto <kisimoto@phys.sci.osaka-u.ac.jp>,
         Jerry Hastings <hastings@bnl.gov>,
         Jack Sandweiss <sandweiss@hepvms2.physics.yale.edu>,
         Hal Spinka <HMS@hep.anl.gov>, hainesjr <hainesjr@ornl.gov>,
         George Stephens <GSFS@mitlns.mit.edu>, George Greene <Greene@bnl.gov>,
         Flemming Videbaek <videbaek@bnl.gov>, Ed Hartouni <hartouni1@llnl.gov>,
         doug <doug@triumf.ca>, Dieter Dehnhard <dehnhard@umphys.spa.umn.edu>,
         Bill Christie <Christie@bnl.gov>,
         Dennis Kovar <DENNIS.KOVAR@science.doe.gov>,
         Elaine Zukowski <zukowski@bnl.gov>, vanzeijts <vanzeijts@bnl.gov>,
         Kirk McDonald <mcdonald@puphed.princeton.edu>,
         John Harris <john.harris@yale.edu>,
         Bill Zajc <zajc@nevis1.nevis.columbia.edu>, Wit Busza <busza@mit.edu>,
         Shojiro Sugimoto <shojiro.sugimoto@kek.jp>,
         Mark Manley <manley@marksun.kent.edu>,
         Joe Comfort <comfort@meg3.la.asu.edu>,
         Mark Sadler <sadler@physics.acu.edu>, Brian Quinn <bquinn@cmu.edu>,
         Bill Molzon <wmolzon@uci.edu>, Prisca Cushman <prisca@umphys.spa.umn.edu>,
         Leonard Mausner <mausner@bnl.gov>, Nick Samios <samios@bnl.gov>,
         Asher Etkin <etkin@bnl.gov>, John Hauser <hauser@bnl.gov>,
         Peter Bond <bond@bnl.gov>, Ray Karol <rck@bnl.gov>,
         Steve Steadman <Stephen.Steadman@science.doe.gov>,
         Harold Kirk <hkirk@bnl.gov>, Michael Marx <marx@sbhep.physics.sunysb.edu>,
         Morgan May <may@bnl.gov>, Charlie Pearson <pearson@bnl.gov>,
         Susan White-DePace <swd@bnl.gov>, Tony Frawley <frawley@rcf.rhic.bnl.gov>,
         Christoph Montag <montag@bnl.gov>, Joanne Beebe-Wang <bbwang@bnl.gov>,
         Tom Throwe <throwe@bnl.gov>,
         Jehanne Simon-Gillo <Jehanne.Simon-Gillo@science.doe.gov>,
         Ronald L Gill <rongill@bnl.gov>, Tom Nehring <nehring@bnl.gov>,
         Gulshan Rai <Gulshan.Rai@science.doe.gov>, Hideto En'yo <enyo@riken.go.jp>,
         TAMURA Hirokazu <tamura@lambda.phys.tohoku.ac.jp>,
         Tonko Ljubicic <tonko@bnl.gov>, Todd Satogata <satogata@bnl.gov>,
         Sanjee Abeytunge <abeytunge@bnl.gov>, "Shrey, Travis C" <shrey@bnl.gov>,
         "Marr, Gregory" <gmarr@bnl.gov>, "kozak@bnl.gov" <kozak@bnl.gov>,
         Jim Jamilkowski <jpj@bnl.gov>, Brian van Kuik <kuik@bnl.gov>,
         Marzia Rosati <mrosati@iastate.edu>,
         Matthias Grosse Perdekamp <matthias@rcf.rhic.bnl.gov>,
         "Cerniglia, Philip M" <cernig@bnl.gov>, cameron <cameron@bnl.gov>,
         Thomas Ullrich <ullrich@bnl.gov>, Phil Pape <pape@bnl.gov>,
         haixin huang <huanghai@bnl.gov>, Wolfram Fischer <wfischer@bnl.gov>,
         Kip Gardner <cgardner@bnl.gov>, Stephan Bueltmann <Bueltmann@bnl.gov>,
         Matthias Grosse Perdekamp <Matthias@bnl.gov>, Matthew <murraymm@lanl.gov>,
         Mark Sakitt <sakitt@bnl.gov>, Abhay Deshpande <abhay@bnl.gov>,
         Abhay L Deshpande <abhay@rcf2.rhic.bnl.gov>, Tom Hayes <hayes@bnl.gov>,
         Brian Cole <cole@nevis.columbia.edu>
    Subject: The lasst weekend in 2001
    
    Hi everybody,
    
    yesterday we had not only beam studies but also an experimental/tunnel
    access. The access period
    was extended by 2 h (from the original plan of 3 h) to repair the
    Westinghouse rheostat and finish the work on the snake heaters. The
    access was followed by various problems (cryo, abort kicker ...) and
    there was no beam before midnight. Early this morning the polarized
    source failed and is currently being repaired. We expect it back online
    within the next hour. At this point Anatoli is still working to set it
    up.
    
    Today we tried another ramp with tune feedback on in blue: with success
    :) !. We are planing one more ramp with feedback in both rings later
    this afternoon (15:??).  We'll keep the beam for collisions in case we
    bring both beams up there with reasonable intensities.
    
    The plan for the weekend is to provide collisions with polarized beam(s)
    while trying to improve intensity and yellow polarization (by applying
    only minor changes ;) ). Yellow polarization is still relatively high at
    injection but almost 0% at store whereas blue drops by less than a
    factor 0.5. Here is the tentative plan for the next days:
    
    date                time                  activity
    ------------------------------------------------------------------------------------------
    
    Sat Dec 29     1h                      CONTROLLED access for PHENIX and
    STAR, to be confirmed/scheduled
    ------------------------------------------------------------------------------------------
    
    Thu Jan 03  8:00-14:00       beam studies, to be confirmed
    ------------------------------------------------------------------------------------------
    
    Thu Jan 03  15:00-17:00    Westinghouse maintenance, PP2PP 1st set
    silicon installation
                                                          to be confirmed
    
    In case you have any questions about the current situation/plan, please
    don't hesitate to call MCR. Have a nice weekend!
    
    --
                                                    \|/
                     Angelika                      (.~.)
                                                  o0(_)0o
    -----------------------------------------------------------
    Angelika Drees (Collider-Accelerator Department, AP group)
    BNL, Building 911b-210
    work: (631) 344 2348
    FAX:  (631) 344 5954
    home: (631) 474 3884
    



    This archive was generated by hypermail 2b30 : Fri Dec 28 2001 - 23:04:07 EST