Shift report 20011114 16:00-24:00

From: Apache (apache@pii3.brahms.bnl.gov)
Date: Wed Nov 14 2001 - 00:17:53 EST

  • Next message: Jens Jørgen Gaardhøje: "Re: RHIC Au x Au Running at 22 GeV"

    ------------------------------------------------------------
    Date: Wed Nov 14 00:17:53 2001, Shift: 16:00-24:00
    Supervisor: BHS, with: 
    Log book#10 pages 137 - 137
    
    Shift Summary:
    ------------------------------------------------------------
    Access all shift to fix STAR problem. Everything was
    completed on time, and at 23:15 final sweeps started.
    
    Hiro worked on getting KDE/gnome to work on the CH machines.
    Currently the programs run OK, but the desktop is 
    agonizingly slow... 
    
    Pedestal runs:
    5786: TPC
    5787: DVM
    5788: Globals
    Installed and OK :-)
    
    So - ready and waiting anxiously for some beam...
    ------------------------------------------------------------
    