Date: Fri Oct 5 08:12:42 2001, Shift: 00:00-08:00
Supervisor: JH Lee, with:
Log book#9 pages 92 - 96
Shift Summary:
------------------------------------------------------------
Beam:
- Stored and Cogged until 0:30 and
a new store at 2:40 until 7:30
(starting ZDC rate at ~430/sec)
- ~2 hours between stores
Data:
- MRS at 60degree 3A
- FRS at 12/3degree 1/5A
- Physics Runs: 5151,5159,5160,5163
- Total 1.5M for MRS and 1.1M trigger1 for this setting
- Next program: MRS 35 degree 4A (2M), FS 12/3 degree 1/5B (1M)
Problems:
- T3(1,2,3) draw high current (~> 60) and
give "T3-map error" almost every second:
Lowered Anode HV by 40V. "T3-map error" is
"almost" gone, currents are below 30. It needs
to be watched.
- "lpr" printer queue for qms_ch doesn't work
(recycling power didn't help, but "pdq" seems to work)
------------------------------------------------------------
This archive was generated by hypermail 2b30 : Fri Oct 05 2001 - 08:13:27 EDT