Shift report 20010915 16:00-24:00

From: Apache (apache@pii3.brahms.bnl.gov)
Date: Sat Sep 15 2001 - 23:59:20 EDT

  • Next message: Apache: "Shift report 20010916 00:00-08:00"

    ------------------------------------------------------------
    Date: Sat Sep 15 23:59:20 2001, Shift: 16:00-24:00
    Supervisor: hiro, with: 
    Log book#8 pages 136 - 138
    
    Shift Summary:
    ------------------------------------------------------------
    1 beam for 2 hr. Then, QLI
    2 run 4746 (data run)
      run 4748 & run 4749 for DVM run
      run4751 pulser run 
    
    3  after pulser run, it is noticed Tile 4-5 have
       a large pedestal.
      By DVM runs, Ramiro noticed the change in DVM measurment.
      (See figures in Log book.)
    ------------------------------------------------------------
    



    This archive was generated by hypermail 2b30 : Sun Sep 16 2001 - 00:00:00 EDT