Shift report 20010904 16:00-24:00

From: Apache (apache@pii3.brahms.bnl.gov)
Date: Tue Sep 04 2001 - 00:01:00 EDT

  • Next message: Apache: "Shift report 20010904 00:00-08:00"

    ------------------------------------------------------------
    Date: Tue Sep  4 00:00:59 2001, Shift: 16:00-24:00
    Supervisor: KH, with: DS, EJ
    Log book#8 pages 71 - 73
    
    Shift Summary:
    ------------------------------------------------------------
    1. Only beam for about 10 minutes.
    2. 3 short runs (4581-4583). 
    3. No detector problems. 
    
    During short beam time, MCR called and said they needed to
    dump beam to turn on some magnets that had gone off.  They
    said they would immediately store, ramp and cog again.
    Then...
    1. Expert working on tripped sextupoles
    2. Experts coming in for sextupole problem; no beam before 21:00
    3. A line crew is in to diagnose a possible ground fault problem
    with 1005B.  No beam until 23:00
    
    We are still waiting at shift end.
     
    ------------------------------------------------------------
    