Date: Wed Aug  8 16:27:08 2001, Shift: 08:00-16:00
Supervisor: JHL, with: 
Log book#7 pages 47 - 48
Shift Summary:
------------------------------------------------------------
1. Machine/Beam
   - Cogged Beam until 9:40
   - Since then no useful beam 
   - Machine is off due to power-saving  
     for 14:00 - 18:00 (Another HOT day here!)
2. Data
   - Physics Data (including from the previous shift)
     for Runs 4064 - 4069 (~400K triggers)
3. Detector Problems/Fix
   - Another broken wire found in T1
     and has been removed (RD,FV)
   - T1 cabling is being modified to run with voltages 
     on Field shaping wires (RD,FV)
   - Bob fixed the T2 read-out problem
------------------------------------------------------------