Shift report 20000815 08:00-16:00

From: http account (http@pii3.brahms.bnl.gov)
Date: Tue Aug 15 2000 - 16:23:20 EDT

  • Next message: http account: "Shift report 20000815 16:00-24:00"

    ------------------------------------------------------------
    Date: Tue Aug 15 16:23:19 2000, Shift: 08:00-16:00
    Supervisor: hb, with: ro
    Log book#4 pages 94 - 96
    
    Shift Summary:
    ------------------------------------------------------------
    1. Beam cogged at 12.40.
    2. Runs 2259 with D2 off
       2261 T1 gating grid closed
       2262 D2 on again
       2265 MT2 at 1290 V
       2266 Mt1 at 1200 V
       2267 Mt1 at 1150 V
    3. RD & CC had an acces, found a loose TPC cable
       Problems controling the magnets, was fixed.
    
    ------------------------------------------------------------
    



    This archive was generated by hypermail 2b29 : Tue Aug 15 2000 - 16:26:46 EDT