brahms runplan as of 11/8

From: Hans Boggild, NBI, Copenhagen (BOGGILD@nbivms.nbi.dk)
Date: Fri Aug 11 2000 - 23:04:02 EDT

  • Next message: http account: "Shift report 20000811 16:00-24:00"

    Dear Brahmsers
    At the run Plan meeting Friday 11th followed by a discussion at the 4 a'clock
    meeting in the counting room the (short-term) plans were defined as :
    
    0) FFS & BFS -> 5 degrees (done) do T1 & T2 studies
    
    1) A short run wanted with GG closed (expert needed)
    
    2) Some test runs with MRS at 90 degrees  for studies of ZDC vs TPC vertex
    
          determination:
        D5 off , one store / one hour 
        D5 on (4 KG) one store / one hour.  
    
    3) Move MRS to 45 degrees (for calibration and background studies)
        D5 off , one store / one houer
        D5 on (4KG) 10 K trig 1
    
    -- during 2 & 3  FFS with D1 at 1/6 of full field, D2 off  (one store)
        rest with D2 on
    
    4)After some study of 2&3 MRS goes back to 90 degrees for data taking. Generally
    with
        95 % of field +/- and 5 % zero field.
    
    
    best regards Hans Bøggild
    