Shift report 20000723 08:00-16:00

From: http account (http@pii3.brahms.bnl.gov)
Date: Sun Jul 23 2000 - 16:39:01 EDT

  • Next message: Konstantin Olchanski: "Re: Shift report 20000723 08:00-16:00"

    ------------------------------------------------------------
    Date: Sun Jul 23 16:39:00 2000, Shift: 08:00-16:00
    Supervisor: FV, with: DO,ZIS
    Log book#3 pages 52 - 59
    
    Shift Summary:
    ------------------------------------------------------------
    1.RHIC continued ramp tuning and injection.
    The beam was very unstable until ~ 12:00.
    2.Few achivements:
    - Run 1892,1894,1898
    - BRAHVO still has a problem with H1,C2,H2,TOFW mainframe. 
    3. No detector problems. 
    ------------------------------------------------------------
    