Shift report 20000720 08:00-16:00

From: http account (http@pii3.brahms.bnl.gov)
Date: Thu Jul 20 2000 - 16:16:15 EDT

  • Next message: http account: "Shift report 20000721 16:00-24:00"

    ------------------------------------------------------------
    Date: Thu Jul 20 16:16:15 2000, Shift: 08:00-16:00
    Supervisor: PC, with: EJK
    Log book#3 pages 33 - 34
    
    Shift Summary:
    ------------------------------------------------------------
    The machine was running at injection energy for short 
    periods and suddenly there was beam at gamma = 70, but 
    when cogged it lasted only for 1 minute 
    ( 2 trigger 6 events ) run no. 1857
    Called and talked to MCR where they said that they would try 
    to accelerate to gamma = 70 for the rest of the day, but
    no stable beam since.
    We took one other run ( write to spool only ) with injection 
    energies, run 1856 where there was 1000 /1300 trigger 4 || 6
    events.
    
    Compiled and moved the new BrNtuple code so it is running
    again.
    
    turned C1 and RICH and TPC ( not anode! ) HV on.
    
    BB has one wide pedestal ( right ch 9 )
    Tof detectors all have some wide pedestal ~2-3 pr detcetor. 
    RICH, tiles and si lacks easy pedestal info. Could not
    view si and tiles pictures in SuperMon.
    
    TPC pedestal programs output was :
    Found 32 suspect pads - what does that mean ?
    
    THat's all folks
    
    
    
    ------------------------------------------------------------
    