Shift report 20000626 16:00-24:00

From: http account (http@pii3.brahms.bnl.gov)
Date: Mon Jun 26 2000 - 23:59:07 EDT

  • Next message: http account: "Shift report 20000627 00:00-08:00"

    ------------------------------------------------------------
    Date: Mon Jun 26 23:59:07 2000, Shift: 16:00-24:00
    Supervisor: JHL, with: TK
    Log book#2 pages 81 - 83
    
    Shift Summary:
    ------------------------------------------------------------
    Machine: Mainly working on preparing ramp to gamma=70
             
    Data: A short run (#1553) at gamma=70 without cogging
          (including no collision events)
    
    Detector: RD had an access to check MTPC2 cabling.  
              MTPC2 anode HV is now set to 1250.
    
    Trigger: See the log book 2 page 81 for descriptions 
    of triggers currently being used for 65 GeV data taking (FV).
    ------------------------------------------------------------
    