------------------------------------------------------------ Date: Mon Jun 26 23:59:07 2000, Shift: 16:00-24:00 Supervisor: JHL, with: TK Log book#2 pages 81 - 83 Shift Summary: ------------------------------------------------------------ Machine: Mainly working on preparing ramp to gamma=70 Data: A short run (#1553) at gamma=70 without cogging (including no collision events) Detector: RD had an access to check MTPC2 cabling. MTPC2 anode HV is now set to 1250. Trigger: See the log book 2 page 81 for descriptions of triggers currently being used for 65 GeV data taking (FV). ------------------------------------------------------------
This archive was generated by hypermail 2b29 : Tue Jun 27 2000 - 00:13:02 EDT