Date: Mon Jun 26 23:59:07 2000, Shift: 16:00-24:00
Supervisor: JHL, with: TK
Log book#2 pages 81 - 83
Shift Summary:
------------------------------------------------------------
Machine: Mainly working on preparing ramp to gamma=70
Data: A short run (#1553) at gamma=70 without cogging
(including no collision events)
Detector: RD had an access to check MTPC2 cabling.
MTPC2 anode HV is now set to 1250.
Trigger: See the log book 2 page 81 for descriptions
of triggers currently being used for 65 GeV data taking (FV).
------------------------------------------------------------